Monday, March 18, 2013

Drainage Work on #10 Fairway



Our recent attempt to drain the terribly wet landing area on the 10th fairway.  We rented an 8' auger attachment for our skid steer.  We then installed a vertical riser pipe which will have a metal grate on top to collect surface water.  We will then be trenching in pipe to divert water into the sump.  We did run into some clay at a depth of 6', which would explain why the area does not drain very well.  The hope is that the sump will collect the water and slowly drain through to the bedrock beneath.

Mike O'Neill, GCS